Morgan Sindall Construction’s London business was appointed by King’s College London to build LIHE, an initiative led by the King’s School of Biomedical Engineering & Imaging Sciences. LIHE builds on King’s expertise in healthcare engineering, and hosts what is said to be ‘a unique ecosystem for taking healthcare engineering innovations from across UK from the bench to the clinic and the market’.
Morgan Sindall Construction explains that the new building is part of the St Thomas’ MedTech Hub, and brings together King’s research excellence, Guy’s and St Thomas’ NHS Foundation Trust’s leading clinical practice, and the sector’s ‘commercial innovation power and talent’, engaging multinationals, SMEs, and start-ups. The business said: “This close collaboration will streamline the R&D process, ensuring that research in healthcare engineering is rapidly translated into new clinical products and solutions.”
The £25m project began in August 2021, and was delivered under the Southern Construction Framework (SCF), a quality-managed collaborative construction framework for public bodies to procure major building works using a two-stage open book process to deliver best value. The four-storey, 3,300 m2 building incorporates open plan offices, meeting rooms, social areas, and a café. Floor to ceiling glass windows, and a large staircase, create a ‘dynamic and light’ interior, while landscaping and a large terrace overlooking the Houses of Parliament maximise the scenic environment.
LIHE’s site has been designed to ‘encourage cross-disciplinary interactions and support new innovations’. Morgan Sindall Construction said: “This ethos is exemplified by the double helix-inspired staircase, which enables social mixing and easy movement. The prominently positioned feature connects the various departments, and creates a spacious, pleasant environment in which to work and engage with others.”
Morgan Sindall leveraged its ‘Intelligent Solutions’ approach to create the staircase, as its central location in the building presented a logistical challenge during construction. To resolve this, a tower crane was positioned in the middle of the development where the staircase would be installed, and then removed and replaced by another to lift in the staircase section by section. Other design features ‘to support cross-pollination of ideas and discussions’ include flexible areas with demountable positions so spaces can be quickly reconfigured for new purposes or as teams change.
Throughout the project, the Morgan Sindall team utilised Intelligent Solutions thinking in a number of other ways. For example, LIHE’s central London location means it is opposite the World Heritage Site of the Palace of Westminster and adjacent to the Grade I listed Lambeth Palace. The site’s historic nature meant the development had to accommodate a Grade II listed mortuary tunnel, which runs directly below the new building.
Being close to vital healthcare facilities, it was important to always ensure access while minimising disruption. To achieve this, a ‘blue light’ road was built across the site to guarantee hospital access, and work was scheduled to create regular quiet times for the nearby children’s ward and sleep clinic.
Sustainability was a key aspect of the project. A reinforced concrete frame incorporating a ‘high-spec’ façade with a very low air permeability rate was utilised, making LIHE a highly energy-efficient building. Several other environmentally-friendly technologies were employed, including sustainable air-handling and fan cooling units, a photovoltaic (PV) panel array, and a grey water harvesting system.